(Festus) The road closure at South Mill Street near Festus Center Drive is back open to normal traffic. The road was closed as workers had to dig 15 feet down to add new sewer mains. Festus City Administrator Greg Camp says the intersection was closed for nearly two weeks, but the construction process continues.

There will be additional road closures in the future as the project continues to West City Park. The three-million-dollar project will eventually result in the closure of the sewage lagoon located near the West Ridge subdivision.